On Indian Point, a campaign position is not operating authority.

Mike Lawler advocates rebuilding and reopening Indian Point. Cait Conley opposes reopening it and proposes investment in other energy sources. The plant's three units are decommissioning, and neither candidate can personally authorize a return to operation.

NY-17 Indian Point public-record guide separating the plant's current decommissioning status, Mike Lawler's reopening position, Cait Conley's opposition and the federal approval question
Current status, candidate positions and regulatory authority are different records. Original information design © 2026 The Rockland Edit; sources checked October 21, 2026. Not a plant photograph, engineering assessment or official ballot.

The state's October 7 amended certification ↗ lists Cait Conley on the Democratic and Working Families lines and Mike Lawler on the Republican and Conservative lines for the November 3 election. Those are two candidates on four party lines. NY-17 includes all of Rockland County.

Start with the plant's current status

The Nuclear Regulatory Commission's June 24 notice ↗ describes Indian Point Units 1, 2 and 3 as permanently shut down reactors undergoing decommissioning. The notice concerns an indirect corporate transfer. It says Holtec Decommissioning International would remain the licensed operator and no physical changes are proposed.

Federal regulation 10 CFR 50.82(a)(2) ↗ says that once permanent-cessation and permanent-fuel-removal certifications are docketed, the Part 50 license no longer authorizes operation of the reactor or placement or retention of fuel in the reactor vessel. That is the legal starting point. It does not mean a future proposal is automatically impossible or approved.

What the candidates propose

Different positions, neither of them an operating authorization
RecordDocumented position or statusWhat it does not establish
Current plant statusUnits 1–3 are permanently shut down and undergoing decommissioning.A corporate transfer is not permission to operate.
LawlerHe calls for rebuilding and reopening Indian Point as part of an all-of-the-above energy strategy.His March statement is advocacy, not an NRC decision or completed project.
ConleyShe opposes reopening and proposes wind, solar, hydro and geothermal investment instead.Her policy page is a campaign proposal, not an enacted program or veto.
H.R. 7796Lawler's introduced bill proposes economic help for nuclear-affected communities.It does not restore Indian Point's operating authority.

Lawler's March 6 congressional statement ↗ calls for the plant to be rebuilt and reopened. The statement also cites his Economic Recovery for Nuclear-Affected Communities Act.

The introduced text of H.R. 7796 ↗ proposes a homebuyer credit, redevelopment initiatives and grants tied to spent fuel or documented tax-revenue loss. It treats eligible facilities as decommissioned or undergoing decommissioning. It does not amend NRC operating authority, direct Holtec to pursue a restart or authorize Indian Point to operate. The reviewed official record shows introduction and committee referrals, not House passage or enactment.

Conley's campaign policy page ↗ says she would stop Lawler's reopening effort and pursue wind, solar, hydro and geothermal projects instead. That establishes her opposition and alternative proposal. It does not establish the condition of the plant, a project timetable or a guaranteed reduction in anyone's electric bill.

Who would actually decide?

A member of Congress can introduce legislation, vote, seek funding, conduct oversight and advocate. A representative does not issue an NRC operating authorization. A real project would first require an owner proposal and facility-specific federal regulatory action.

The NRC's Palisades record shows why that distinction matters. In that separate case, the agency said a license transfer was necessary but not sufficient to authorize operation; the owner also sought an exemption and multiple license amendments. Palisades is a concrete example, not proof that Indian Point would follow the identical pathway.

State and local records add another layer, but they should not be stretched. A 2021 Public Service Commission Joint Proposal adopted in Case 19-E-0730 ↗ includes a provision about Holtec proposing new reactors with support or non-opposition from identified governments. The text does not expressly resolve a hypothetical restart of the existing units, so this guide does not turn it into a universal local veto.

The current New York proceeding is not a reopening vote

Holtec's May 7 petition in Case 26-E-0314 ↗ seeks a ruling or approval for an intra-corporate reorganization. It says the Indian Point companies would continue to own the site and assets and hold the NRC licenses and decommissioning trusts; HDI would remain decommissioning operator. The filing says the transaction would make no physical change and no change to ongoing decommissioning.

The PSC's October 8 schedule notice ↗ extends initial comments to November 18, 2026, and replies to December 21, after Holtec Nuclear Corporation postponed its announced initial public offering. Residents may comment on that corporate-transfer request, but the proceeding is not a public referendum on restarting Indian Point.

The careful bottom line

The reviewed records establish a real ballot choice: Lawler advocates reopening; Conley opposes it and proposes other energy investment. They also establish that the units remain in decommissioning and that neither candidate can personally restore operating authority.

No active restart project is established by the records reviewed for this guide. That is narrower than claiming no filing exists anywhere. The records also do not support a restart date, price, household-bill effect, engineering verdict or safety conclusion.

More in our NY-17 issue guides: Haitian TPS: separate a House vote from present status → · Congressional stock trading: a vote and a divestment proposal are different records → · SALT: a higher cap is not repeal →

Sources checked October 21, 2026: New York's October 7 amended election certification; Lawler's March 6 statement; Conley's current policy page; the introduced H.R. 7796 text; the NRC's June 24 Indian Point corporate-transfer notice; current 10 CFR 50.82; Holtec's May 7 New York petition; the PSC's October 8 comment-schedule notice; and the 2021 PSC order and Joint Proposal. Official records control plant status, legislation and proceedings; candidate-authored pages establish positions only. No interview, site visit, engineering analysis, endorsement, predicted approval or household savings claim is represented.